Which technical review is most likely to be found only in the Production and Deployment phase?

Prepare for the DAU Program Management PM Exam with targeted quiz questions. Study using flashcards and multiple choice questions, each complete with hints and explanations. Boost your readiness for the exam!

The Physical Configuration Audit (PCA) is specifically associated with the Production and Deployment phase of a program's lifecycle. This review is conducted to ensure that the product being produced meets the specified requirements and is in full compliance with the design and performance specifications. The PCA verifies that the system's physical configuration is consistent with the design documentation and confirms that the hardware and software components are integrated as intended.

This audit serves as a critical checkpoint before a product is deployed to ensure that what has been built aligns with what was designed, allowing for effective quality assurance and risk management in this phase. It helps in validating that all necessary revisions and configurations have been accurately implemented before the system becomes operational.

In contrast, a Design Review, System Requirements Review, and Technical Performance Measurement tend to occur in earlier phases of the project. These reviews focus on aspects like concept verification, requirement validation, and ongoing assessments of performance metrics, which are not necessarily tied exclusively to the production and deployment phase. The PCA stands out as uniquely positioned within the final stages, emphasizing its critical role in confirming readiness for production and subsequent operations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy