Which activity is NOT conducted during the Production and Deployment Phase?

Prepare for the DAU Program Management PM Exam with targeted quiz questions. Study using flashcards and multiple choice questions, each complete with hints and explanations. Boost your readiness for the exam!

During the Production and Deployment Phase, the activities focus on making a system ready for operational use and ensuring it meets the required standards and functionality. One of the core activities is system testing, which verifies that the system operates as intended and meets project objectives. Production validation also plays a crucial role, as this ensures the final product is suitable for release based on testing outcomes.

Deployment planning is another key activity in this phase as it involves strategizing how the system will be introduced to users and integrated into the existing environment, ensuring a smooth transition.

The decision regarding the Development Request for Proposal Release is not typically conducted during this phase. Instead, that activity is usually part of the earlier stages in the project lifecycle, focusing on defining project requirements and sourcing potential contractors or solutions before moving into production. Thus, the process of preparing and deciding on the RFP is not aligned with the activities during the Production and Deployment Phase, highlighting why this option is not conducted during that stage.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy