The Preliminary Design Review (PDR) confirms the ________ and readiness to proceed into detailed design work.

Prepare for the DAU Program Management PM Exam with targeted quiz questions. Study using flashcards and multiple choice questions, each complete with hints and explanations. Boost your readiness for the exam!

The Preliminary Design Review (PDR) is a critical milestone in the engineering and program management process, specifically in the development of complex systems. During the PDR, the project's design is assessed to confirm that it meets the allocated baseline. The allocated baseline includes the requirements, specifications, and configurations that have been set forth by project stakeholders and serves as the foundation for all subsequent design and development activities.

Confirming the allocated baseline is essential because it ensures that the project remains aligned with its operational needs. This review serves to validate that the design is not only feasible but also adheres to the technical parameters and constraints established at the project's outset. Once the PDR has confirmed the allocated baseline, it indicates that the project is ready to advance into the detailed design phase, where specific components and systems will be developed in depth.

While design maturity, technical capability, and performance goals are important concepts, they do not specifically capture the essence of what is confirmed during a PDR as clearly as the allocated baseline does. The allocated baseline serves as the control point for both planning and future assessments, making it the most relevant focus for this phase of the project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy